Caltrans Logo

Widen NB from 0.4 mile north of SR-91 to 0.1 mile north of Lambert Road

Description: In Placentia and Brea, from just north of Route 91 to just north of Lambert Road. Northbound widening.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Brea, Fullerton, Placentia
Zip Code 92821, 92831, 92835, 92870
 
Senate District
29, 33
Assembly District 72
Congressional District 40, 42
 
Caltrans District
12
 
 
County/State Route Orange 57
Postmile Begin/End 16.4 21.1
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  19860    933  
Lane Miles Added (Mixed)  5.1    2.4  
Peak Period Time Savings (minutes)  499091    23760  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Orange County Transportation Authority Rose Casey (714) 560-5729   rcasey@octa.net
Design (PS&E) Phase
Orange County Transportation Authority Rose Casey (714) 560-5729   rcasey@octa.net
Right of Way Phase
Caltrans Adnan Maiah (949) 724-2089   adnan_maiah@dot.ca.gov
Construction Phase
Caltrans Adnan Maiah (949) 724-2089   adnan_maiah@dot.ca.gov
 
Corridor System Management Plan
Caltrans Ryan Chamberlain (949) 724-2899   ryan.chamberlain@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$70,000 $10,763 $80,763
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$70,000 $-48,757 $21,243
Non Budgeted ETC
$0 $0 $0
 
Total**** $140,000 $-37,994 $102,006

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,662 $-494 $1,168 $1,168
Design(PS&E)
$12,240 $2,235 $14,475 $13,840
Right of Way
$1,550 $3,450 $5,000 $4,320
Construction
$124,548 $-43,185 $81,363 $81,378
 
Total* $140,000 $-37,994 $102,006 $100,706

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2005 

12/01/2007 
 

 
06/01/2005 

12/01/2007 
100  06/01/2005 

11/30/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2008 

11/01/2009 
 

 
03/01/2008 

11/01/2009 
100  02/18/2008 

12/28/2009 


-2 
Begin Right of Way Phase

End Right of Way Phase
08/01/2008 

11/01/2009 
 

 
08/01/2008 

11/01/2009 
100  12/01/2007 

06/03/2010 


-7 
Begin Construction Phase

End Construction Phase
10/01/2010 

07/01/2014 
 

 
10/01/2010 

07/01/2014 
100  10/12/2010 

11/06/2014 


-4 
Begin Closeout Phase

End Closeout Phase
07/01/2014 

07/01/2015 
 

 
07/01/2014 

07/01/2015 
100  11/07/2014 

06/16/2016 
-4 

-12 
Corridor System Management Plan
Adoption Date     05/01/2009  100  09/01/2010  -16 
Implementation Date     06/01/2009  10/01/2010  -16 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 19860 933
Lane Miles Added (Mixed) 5.1 2.4
Peak Period Time Savings (minutes) 499091 23760

Bond Funding Cost
Adopted:
$70,000,000
Current Approved:
$82,175,000
Actual Expenditures:
$79,640,000

 

Status as of December 31, 2023.